Time and action plan for Apparel Merchandising
Time and action plan for merchandisers:
The
time and action plan (TNA or T&A Plan) is an important tool for a
merchandiser to enlist his day-to-day activities or to enlist the different
operations involved in the process of completing an order. This process
involved various department and different people in the manufacturing. Hence,
this T&A calendar / plan helps the merchandiser to analyses every
individual operation with the aspect of, when to start? When to end? Is the process according to the plan? Or is
there any deviation with the activity?
In short, a time and action calendar defines the ideal date/time period within which the major activities of an
order should occur against a scheduled de- livery. In general, the merchandisers
will develop list of activities need to
be performed for an order in a spreadsheet in a column, the expected
date of completion on next column and
the actual completion date on the very next column.
However, this time, and action plan is not simply a data entering
process, it is also about scientifically working out the activity
duration, logically determining the
preceding and succeeding
activities. The main
Purpose of time and action plan is to cross
check the each activity related to a
particular order in frequent interval. The main advantage of the time and
action plan is its graphical representation (Gantt chart). Hence, anyone can understand the information out of
it without any technical background. After the preparation of TNA calendar,
merchandiser can list down their daily “to-do-list” and taking it one by one.
As per TNA schedule processes can be executed on timely basis to track whether
an order is on track or it will get delayed. To
prepare a time and action plan, the merchandiser re- quires the
following details:
1) Extensive process
flow of an order from the sampling
to dispatchwith tasks to
be performed on each activity
2) Detailed production capacity of various
departments of their unit. In some cases, the merchandiser needs to know their
vendor’s production capacity also
3) Tentative lead time details of various raw
material and buffer time required
for each department
4) Style complication in
each department level, both in technical aspects
and also in terms of throughput time of different departments
5) Duration of transportation, shipment and
logistic facility for the par- titular customer and exact delivery date to the
customer
6) Availability of the special machines
/ technology and their possible Influences
7) Details regarding the local and national
level holidays – in his/ her company and also holiday information about
customers / vendors, from where the raw material imported or to whom the
products need to be delivered
8) Complication associated with the trims and
accessories sourcing and manufacturing
9) Government and political policies of concerned countries
10) Response
time of customer / buyer at various stages.
(A)Factors to be considered while making Time and action plan:
•
Production capacity of
plant
•
Style type of merchandise
•
Festivals of manufacturing country
•
Holidays
•
Shipment details
•
Festivals of country from where raw material is imported
•
Logistics facilities
•
Lead time estimated by buyer
•
Style complications
•
Fabric and trims manufacturing complications
•
Buffer required from each department
•
Political stability of the country
•
Flexibility of freight
forwarder
•
Response time from buyer at different stages
• Lead
times of various activities like L/C payment, custom
clearance, etc.
•
Cut-off dates for shipments
A successful time and action plan helps
to streamline the pre-production activities at different level. The chart also
clarifies information about delays in day to day basis. This activity chart
helps the merchandiser to monitor the sub or minor activities under
each task. Out of this preparation work, the complications come along with the
sampling department. Since, the approval from buyer or from the higher
management of his / her own company is necessary after each of the sampling
stage, the unexpected delays in sampling process makes the merchandiser
uncomfortable. Hence, during the TNA preparation, sufficient buffer time need to be provided
between the processes, based on individuals
experience. The Figure mention details
the various key activities which need to be performed by a merchandiser at
various levels of sample development.
Figure:Influencing key activities from the sample department
From the
production point of view, there are
few other critical process which has direct influence on the time and action
chart preparation. The operations
and their influencing factors were listed in following Table;
Table .Tentative lead time for different key
activities
S.
No.
|
Process
name
|
Lead
time details
|
1
|
Fabric approval
|
•
For lab dip – 15 days for a single time (based on the
quality expectations and facility available Merchandiser can plan 10–30 days)
|
2
|
Prints,
trims and accessories
|
•
15–25 days for the approval is must. If complicated
styles / special materials used lead time can be extended up to 30 days
|
3
|
FPT
|
•
Most of the time performed by the third party (Buyer
recommended internationally accredited testing organizations)
•
5
days to 1 week time can be provided as lead
time
|
4
|
Fabric
and trim sourcing
|
•
Very time consuming process which includes
desk loom and lab dip approvals, trim and art work approval, FPT approval
•
For
sourcing solid dyed – 30 days
•
yarn
dyed – 45 days
Fabric dyed – 55–60 days
•
Can
be given as a lead time in T&A plan
•
For sourcing of Trims – Based on availability and place of sourcing 30–45 days can be given
|
5
|
Production
department
|
•
Sourcing
department delays will be considered
•
Based on the complexity in the sourcing process, the
buffer time can be allotted for cutting department
•
Production department start date from the very next day
(or 1 or 2 days) from the cutting department (based on production capacity)
•
Based on factory efficiency and capacity the lead time
for each department can be allotted by considering the shipment date
|
Other than
these key activities, a merchandiser should always remember the style
complication of the particular labour, the operator efficiency of the factory, skill level, technology available with the facility and initial lag of production during the manufacturing. By
considering these factors, a merchandiser
can allocate buffer time / lead time for each activity and sub-activity.
Comments
Post a Comment